The single machine commissioning phase is started at Vietnam northern nitrogen project

Release time: 2014-05-19  Browse: 1774

 

On April 10 to 12, the eighth high level meeting of Vietnam Northern nitrogen project was hold at project site which means single machine commissioning phase will be started at Vietnam Northern nitrogen project. Working procedure of each specialty and each department was detailed by project department and day workload quantification is implemented; all measures were taken to catch schedule, improve quality, ensure safety; all of above is to ensure the compound and urea area would be completed at May 31. During the commissioning coordination meeting, site manager Zeng lide emphasized that each specialty must work together to fine and solve problem at the leading of equipment specialty; at the premise of ensuring quality and safety, commissioning work must be completed successfully.