2015 annual overhaul of Bangladesh KAFCO chemical fertilizer plant was started officially

Release time: 2015-04-15  Browse: 1530

     Known at 7 April, 204 Company staffs were in position who would take part in the overhaul of Bangladesh KAFCO chemical fertilizer plant; which meant 2015 annual overhaul of Bangladesh KAFCO chemical fertilizer plant was started officially.

    This overhaul work was divided into two parts: main contractor and borrowing worker; in which, borrowing worker is mian for the work of compressor, static equipment and part pipe replacing, including fitter, plumber, lifting worker, instrument staff ; they are total 152 staffs and the duration is 35 days.main contractor part is the replacing work of sixth layer to eighth layer radiation wall brick of first reformer, including furnace instruction worker, liftingworker and fitter; they were total 52 staffs; day shift and night shift working system was used; and they wolud execute construction under the union supervision and direction of design unit Japan CKK company and Owner KAFCO company.