On December 22nd, the first bridge erecting machine of Dubai R1013 Road and Bridge Project successfully passed the performance test, marking that R1013 Project will officially enter into the assembly stage of precast box girder bridge deck. It is learned that the test of the bridge erecting machine is deflection deformation test, which tests the bending degree of main beam and the recovery degree after unloading when the bridge erecting machine exceeds the design load by 25%, so as to determine whether the bridge erecting machine meets the hoisting requirements. A total of 11 box girders were hoisted in this test. After 16 hours of intensive operation, the first bridge erecting machine successfully passed the test.