The Nigeria Dangote Refinery Project Team has achieved the pressure test target for five consecutive months from July to November since the introduction of monthly target reward and punishment system in July this year. There is a total of 916 pressure test packages in the MHC plant, that is, roughly 650,000 inches meters. As of December 6th, for package wise, the project team has completed pressure test for 377 packages, accounting 41.16% of the total volume, while for the length of pipeline wise, it is 203,400 inch-meters, 31.30% of the total. In the coming days, the pipeline team will maintain their outstanding performance and complete the various construction plans formulated by project team.
With the joint efforts of the project team, MHC installation workers overcome various difficulties and challenges in the summer heat and made breakthrough progress in promoting the pressure test.