the installation of concrete prefabrication pipe rack of Malaysia RAPID project was started

Release time: 2016-05-25  Browse: 946

At 17th may, lifting of the first concrete prefabrication pipe rack of Malaysia RAPID project was finished successfully. The length of this concrete column is 18m and weight is 33t.
According to contractual specification and construction overall planning, project department would finish the installation work of 268 concrete prefabrication columns and 1086 concrete prefabrication beams in following three months in which the most heavy prefabrication column is 46t and the total lifting amount would be more than 20,000t.