The power receiving of 4.16KV substation of Saudi Arabia phosphate factory has been finished successfully

Release time: 2016-11-29  Browse: 1058

 

At 3:08 p.m., 27th Nov, The power receiving of 4.16KV substation of Saudi Arabia phosphate factory has been finished successfully which meant anther significant milestone of phosphate factory has been achieved.

The 4.16 KV substation of Phosphate factory includes two 34.5/4.16 KV transformers, four 4.16/0.48 KV transformers and 146 electrical panels and cabinets. After the power receiving has been finished, single commissioning work of phosphate factory would be started soon. Next, the power would be transmitted to each device area through substation and dynamic device single commissioning work for each device would also be started soon.