At 19:08 on December 4th, the local time, the Primary Reformer was successfully ignited at the UNF project in Uzbekistan, it means that up to 210 hours furnace drying phase was carried out. The one-time igniting of the converter has been fully affirmed by the owner and the general contractor.
Along with the starting of reformer drying, commissioning with water for PA compressor and ES102 decarburization system will also be started in succession, and whole staff of UNF project in Uzbekistan will make every effort to get the goal of completion.