The Concrete Pouring of the Foundation Column of 20,000 Cubic meters Capacity of Storage Tanks in Xinjiang Zhongan Xinzi LNG Project was Completed Successfully

Release time: 2020-05-18  Browse: 1568

On the morning of May 13th, pouring of concrete for the foundation column of a storage tank with capacity of 20,000 cubic meters in Xinjiang Zhongan Xinzi LNG Project started. Total 136 reinforced concrete columns were successfully poured in the next day. The project team never relaxes on the epidemic prevention and control during pouring works, and strictly arranged the construction plans and steps in accordance with the requirements of the "Fine Management Manual". It took only 19 hours to finish the pouring of 136 foundation columns. This fully demonstrated the ability of project team to organize scientifically and execute accurately and work together. It also laid a solid foundation for the subsequent standardization and normalization of concrete pouring work.