10,000 m3 Storage Tank Foot of Xinjiang Zhongan Xinzi LNG Storage Tank Project Was Successfully Poured

Release time: 2020-07-08  Browse: 1666

On July 1st, 10,000 m3 storage tank foot concrete pouring work in Xinjiang Zhongan Xinzi LNG Storage Tank Project was completed, marking the completion of the most important civil milestone, which created the favorable conditions for the subsequent installation work of storage tank. Summing up the previous two pouring experience, the project team organized a concrete pouring quality assurance team to inspect the commercial concrete station to ensure the high-quality supply of concrete. The concrete pouring of 10,000 m3 storage tank top foot is mass concrete pouring with limited time line and heavy work. With the active cooperation of all the personnel of the project team, the pouring work was successfully completed at 10 a.m. on July 1st.